warehouse construction method statement
Article: Method Statement for Warehouse Construction
1. Introduction
The construction of a warehouse is a complex process that demands precise planning, robust engineering, and adherence to safety and quality standards. This warehouse construction method statement provides a step-by-step guide covering all essential aspects — from site preparation to handover — ensuring the project is completed efficiently, safely, and in compliance with Saudi Building Code (SBC), ASTM, and ACI standards.
For contractors like Dorar Tammam Contracting (DTC), BoldTarget, and other leading companies in the Eastern Province, Dammam, Khobar, Riyadh, and Jeddah, method statements serve as the backbone of every industrial and PEB warehouse project.
Keywords: warehouse construction, method statement, warehouse building, PEB warehouse, industrial warehouse, construction in Saudi Arabia, Dammam contracting company, steel structure erection, site preparation, concrete foundation, quality control, safety procedures, project handover
2. Objective
The main objective of this method statement is to define and implement a standard process for all activities associated with warehouse construction. It ensures uniform quality, consistent safety measures, and proper coordination between all trades — civil, structural, mechanical, and electrical — while achieving the client’s specifications and project deadlines.
Keywords: method statement objectives, construction methodology, industrial warehouse Saudi Arabia, quality management system, project execution plan, warehouse building construction
3. Scope of Work
The scope of this document includes the complete construction cycle of a steel structure warehouse:
-
Site clearance and layout works
-
Excavation, backfilling, and foundation construction
-
Structural steel and PEB erection
-
Roof and wall cladding installation
-
Floor slab casting and finishing
-
Masonry, doors, and architectural finishes
-
MEP installations (if applicable)
-
External works and landscaping
-
Testing, commissioning, and final handover
Local Keywords: Dammam warehouse construction, Riyadh industrial building, Jeddah steel structure project, Khobar contracting works, Jubail warehouse, Sudair industrial city factory, warehouse project Saudi Arabia
4. Responsibilities
| Role | Responsibility |
|---|---|
| Project Manager | Overall project execution, progress monitoring, and coordination with consultants and clients. |
| Site Engineer | Supervises work as per drawings, manages manpower, and ensures site quality. |
| QA/QC Engineer | Maintains inspection and testing records, approves materials, ensures compliance with ITP. |
| HSE Officer | Implements safety protocols, conducts toolbox meetings, and enforces PPE use. |
| Foreman / Supervisor | Directs daily site activities and manpower allocation. |
Keywords: site engineer, QA/QC engineer, project manager, safety officer, construction supervision, HSE plan, project responsibilities
5. Materials and Equipment
Materials
-
Ready-mix concrete (25–35 MPa)
-
Reinforcement steel (Grade 60)
-
Structural steel (ASTM A36, A572)
-
PEB materials and accessories
-
Roofing and cladding panels
-
Anchor bolts, fasteners, insulation materials
-
Masonry blocks, cement, and paints
Equipment
-
Excavators, dump trucks, and compactors
-
Mobile cranes and boom lifts
-
Welding machines and torque wrenches
-
Concrete mixers, pumps, and vibrators
-
Survey instruments (total station, laser level)
Keywords: warehouse construction materials, steel structure equipment, concrete mixer, crane erection, welding tools, construction machinery Saudi Arabia
6. Construction Procedure
6.1 Site Preparation
-
Conduct a detailed topographical survey.
-
Clear and grade the site, removing debris and vegetation.
-
Set out gridlines and reference points using a total station.
-
Establish temporary site offices, safety signage, and storage areas.
Keywords: site preparation, earthwork, site clearing, setting out, topographic survey, construction site layout
6.2 Excavation and Foundation Works
-
Excavate foundation trenches to the specified depth.
-
Compact the subgrade to 95% Modified Proctor density.
-
Pour lean concrete blinding (100 mm thick).
-
Fix rebar and formwork as per approved shop drawings.
-
Cast concrete footings and columns using approved mix.
-
Conduct slump and cube tests to ensure concrete quality.
Keywords: excavation works, concrete foundation, soil compaction, reinforcement steel, concrete casting, Dammam warehouse foundation
6.3 Anchor Bolts and Base Plates
-
Position anchor bolts using steel templates for accuracy.
-
Check bolt alignment, verticality, and elevation before pouring concrete.
-
Once concrete cures, fix base plates and verify level tolerance within ±3 mm.
Keywords: anchor bolts installation, base plate leveling, structural alignment, steel column base preparation
6.4 Structural Steel Erection
-
Offload steel components in a designated area and inspect for damage.
-
Erect columns and rafters using cranes under supervision.
-
Tighten bolts as per torque specification.
-
Install bracings, purlins, and side rails sequentially.
-
Conduct bolt torque checks and welding as per WPS (Welding Procedure Specification).
Keywords: steel structure erection, pre-engineered building erection, warehouse steel frame, welding WPS, torque testing, DTC warehouse project
6.5 Roofing and Cladding Works
-
Lay insulation sheets if required by design.
-
Fix roof panels starting from leeward side to avoid water ingress.
-
Overlap sheets correctly and apply sealant on joints.
-
Install wall cladding, trims, and flashing.
-
Ensure alignment, color uniformity, and aesthetic finish.
Keywords: roof cladding installation, sandwich panels, wall sheeting, insulation, flashing, waterproof roof construction
6.6 Floor Slab and Concrete Finishing
-
Prepare the sub-base with compacted granular material.
-
Lay vapor barrier and reinforcement mesh.
-
Pour concrete in panels using laser screed for precision.
-
Apply surface hardener or power float finish.
-
Cure slab for minimum 7 days using curing compound.
Keywords: concrete floor slab, laser screed, floor finishing, warehouse concrete floor, curing process, floor hardener application
6.7 Masonry, Doors, and Finishes
-
Construct masonry block walls and apply plastering.
-
Install steel doors, roller shutters, and aluminum windows.
-
Paint internal and external walls with industrial-grade coatings.
Keywords: masonry works, painting, roller shutter installation, industrial door, wall plastering, architectural finishes
6.8 MEP Installations (If Applicable)
-
Install electrical conduits, lighting, and power distribution.
-
Lay plumbing pipelines and drainage networks.
-
Install fire alarm, firefighting, and HVAC systems.
Keywords: MEP installation, electrical works, plumbing, HVAC ducting, fire fighting system, mechanical services
6.9 External Works
-
Construct access roads, parking areas, and footpaths.
-
Install stormwater drainage and septic tanks.
-
Landscape and install perimeter fencing.
-
Ensure proper slope for stormwater discharge.
Keywords: external works, road construction, drainage system, fencing, landscaping, warehouse site development
7. Quality Control (QA/QC)
Quality is maintained through strict adherence to the Inspection and Test Plan (ITP). Each stage undergoes inspection and documentation:
-
Material inspection upon delivery
-
Concrete and steel testing (compressive strength, rebar tensile tests)
-
Weld inspections (visual and NDT if applicable)
-
Bolt torque verification
-
Dimensional and alignment checks
Keywords: quality control, ITP, QA/QC inspection, concrete test, welding inspection, bolt torque test, project quality assurance
8. Health, Safety, and Environment (HSE)
Safety is a top priority throughout the warehouse construction.
-
Conduct induction training for all personnel.
-
Provide PPE such as helmets, gloves, and safety boots.
-
Use certified lifting equipment and inspect scaffolds.
-
Ensure fire extinguishers and first aid kits are accessible.
-
Maintain clean walkways and spill control procedures.
Keywords: safety procedures, PPE, HSE compliance, toolbox talk, accident prevention, construction safety Saudi Arabia
9. Sequence of Work
-
Site setup and mobilization
-
Excavation and foundation construction
-
Structural steel erection
-
Roofing and wall cladding
-
Floor casting
-
Masonry and finishing works
-
MEP installation
-
External works and landscaping
-
Final inspection and project handover
Keywords: construction sequence, project scheduling, workflow plan, warehouse construction stages
10. Documentation and Handover
Upon completion:
-
Submit as-built drawings and test certificates
-
Provide QA/QC documentation and HSE reports
-
Conduct final walkthrough with client and consultant
-
Rectify snag list (if any) before final acceptance
Keywords: project handover, as-built drawings, completion documents, quality reports, final inspection, DTC project completion
11. Conclusion
This warehouse construction method statement ensures structured execution, safety, and compliance across all project phases. With the growing demand for industrial and logistics buildings across Saudi Arabia, following this systematic approach ensures efficiency, cost control, and durability in every project.